On Site Construction Steps
Step By Step Cabin Construction Pictures  |   Completed Home Pictures  |   Step By Step Home Pictures
Outer Walls – Usually erected in 4-5 days (assumes prior completion of foundation).
Log corners are then installed to give an insulated, draught free structure.
Gable Sections are pre assembled at the factory and lifted into place, usually after 1 week.
Roof Trusses – Installed after gable –Roofing assembly can start on 8th day depending on home size and roof composition material. Steel roof lathe system requires a little longer.
Completed Construction