Outer Walls – Usually erected in 4-5 days (assumes prior completion of foundation).
|
 |
Log corners are then installed to give an insulated, draught free structure.
|
 |
Gable Sections are pre assembled at the factory and lifted into place, usually after 1 week.
|
 |
Roof Trusses – Installed after gable –Roofing assembly can start on 8th day depending on home size and roof composition material.
Steel roof lathe system requires a little longer.
|
 |